November 15, 2026 · Brendan Hogan, Founder, GridPermit

Gas Turbine Makers Are Now Taking Reservations for 2032 Delivery. Here Is What That Does to Data Center Power Plans.

GE Vernova has 122 GW of gas turbines sold or reserved against roughly 20 GW a year of output, Siemens Energy and Mitsubishi are booked into 2028 to 2030 and beyond, and developers are turning to engines and fuel cells that arrive in 18 to 24 months. The numbers, and what they mean when you diligence a site.

If you are a direct purchaser of generation equipment, whether turbines, reciprocating engines or fuel cells, I'm happy to connect you with opportunities we have available through GridPermit. Send me a connection or message me directly and tell me what you are buying and when you need it.

On October 28th, GE Vernova told investors that the gas equipment it has under contract, counting firm orders and slot reservations together, grew from 116 GW to 122 GW in the third quarter, and that it expects to exit 2026 with at least 130 GW. In the same quarter it shipped 5 GW. Utility Dive reported that the company is now taking reservations for delivery in 2032.

That is the number to hold onto if you are building a data center that needs its own power. One of the three major turbine makers is now quoting a new buyer a delivery date six years from now.

The numbers behind the wait

GE Vernova's third-quarter release splits the 122 GW into 64 GW of equipment backlog and 58 GW of slot reservation agreements. The company signed 11 GW of new contracts in the quarter, 8 GW of them slot reservations and 3 GW orders, and converted 13 GW of earlier reservations into orders. Utility Dive notes the total started 2026 at 83 GW, and that the 6 GW added in the third quarter was a much slower pace than the double-digit quarterly gains earlier in the year.

How fast can that backlog be worked off? GE has said it is producing at about 20 GW a year, with a plan to reach 24 GW by 2028 and 30 GW by 2030. Divide 122 GW by 20 GW and you get a little over six years. That is my arithmetic, not a company statement, and it overstates the wait for any single buyer because 58 GW of the total are reservations, not firm orders, and some of the output is for other markets. But it explains why the quoted delivery year keeps sliding. According to Oilprice's account of GE's July earnings call, the company was then taking reservations for 2031 delivery. By the October report, the year was 2032.

The other two large makers tell a similar story. The same Oilprice article reports that Siemens Energy ended its fiscal third quarter on June 30th with a 69 GW gas turbine backlog after booking 15 GW and shipping 6 GW, and describes lead times of three years or more. Turbomachinery Magazine reported Siemens Energy's gas services orders for the quarter at 9.97 billion euros and its segment backlog at 73 billion euros, though it did not give a gigawatt figure. For Mitsubishi Heavy, Oilprice reports a large-frame backlog of 35 GW on August 6th, up from 23 GW a year earlier, with orders booked in the quarter scheduled for delivery between 2028 and 2030. Mitsubishi's CFO said the company is being selective about the projects it takes.

Oilprice also reports that the average time to deliver a new combined-cycle plant has stretched from about 3.5 years in 2023 to roughly five years now, with some heavy-duty frames taking about seven. Those are that article's figures, not a regulator's, so treat them as a reasonable picture of the market and not a quote.

What the wait is doing to price

Scarcity shows up in the cost per kilowatt. Oilprice cites BloombergNEF putting the average combined-cycle project at $2,157 per kW last year, up from under $1,500 in 2023, and GridLab data showing projects targeting 2030 and 2031 routinely reporting $2,000 per kW or more. Utility Dive reports that GE Vernova's third-quarter order pricing was more than 20% above the fourth quarter of 2025, and that its full-year 2026 order pricing is on track to rise about 50%. Part of that comes from mix, since the company sold more aeroderivative units, so the quarter-to-quarter swings are noisy. The direction over two years is not.

Data centers are not the whole line

It is easy to read all of this as an AI story, and the data center share is real, but Utility Dive reports that GE Vernova puts about 80% of its demand with traditional customers and 20% with data centers. Utilities replacing retiring plants and serving load growth are standing in the same queue. A data center developer is not just competing with other data centers for a turbine. It is competing with the utility that would otherwise serve the site.

What developers are doing instead

Many are not waiting. An Enverus forecast reported by Power Engineering on October 5th expects behind-the-meter power to serve 25.5 GW of new U.S. industrial demand through 2030, and 22.5 GW of that, or 88%, is data centers. To serve it, Enverus counts 31.6 GW of new generation, of which 29.6 GW is gas-fired.

The mix matters more than the total. Reciprocating engines, small and medium-frame gas turbines and fuel cells make up 61% of the gas-fired capacity Enverus tracks, and those technologies reach commercial operation in roughly 18 to 24 months. Large-frame combined-cycle plants can take as long as 80 months. Modular fleets also need less spare capacity: Enverus puts the overbuild for engines and fuel cells as low as 1.1 times demand, against about 1.5 times for large-frame plants. In other words, the shortage is of one kind of equipment, and the market is already moving to the kinds that can be delivered.

What it means when you diligence a site

My view is that the equipment slot is now a gating item on the same level as the interconnection queue, and most site reviews still treat it as an afterthought. If a site's plan depends on onsite generation, the questions I would ask before anything else are who holds the equipment slot, what delivery year is on it, and whether it is a firm order with a deposit or only a reservation. Fifty-eight of GE's 122 GW are reservations, which shows how loosely the word booked can be used.

Then ask what the plan is if the slot slips. A bridge of engines or aeroderivatives in front of a later large-frame plant, or a grid connection that arrives before the turbines do, are different risk profiles, and a buyer should be told which one they are being sold. And check the other constraints that do not go away because equipment arrives: the air permit, the gas supply and pipeline capacity, and the local zoning for a power plant next to a data center.

None of this makes the shortage a reason to stop. It makes the buyers who have equipment, or a credible path to it, the scarce party in the market. If that is you, send me a connection or message me directly. We are happy to talk about the opportunities we have available.

#GridPermit #DataCenters #SiteSelection #DataCenterDevelopment #PowerGeneration #GasTurbines #DataCenterEnergy #PowerInfrastructure #HyperscaleDataCenters #AIInfrastructure #BehindTheMeter

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report