AWS Broke Ground on Its $7 Billion Indiana Data Center This Week. The State Law Meant to Make Data Centers Pay Localities Got Negotiated Down to a Penny First.
AWS and NIPSCO broke ground November 12th on a $7 billion Jasper County campus with $798 million and a water cap already locked in writing. The Statehouse's own version of that deal didn't hold.
On Thursday, November 12th, officials from Amazon Web Services and the local utility NIPSCO picked up ceremonial shovels in a soybean field outside Wheatfield, Indiana — population a little over 1,000 — and broke ground on a data center campus AWS is calling Project Rise. The number attached to it is $7 billion. Nine buildings, eventually, spread across 304 acres that NIPSCO sold directly to Amazon. "Today's groundbreaking is about much more than a new facility," said Rick Calinski, NIPSCO's director of economic development and public affairs, at the ceremony, framing it as a long-term bet on the region rather than a one-time construction project. Scott Eckhardt, an AWS economic development principal, spoke alongside him.
Lines like that get said at a lot of groundbreakings. What makes this one worth taking seriously is how specific the paperwork behind it already is, and how little of it is still a promise. Project Rise is also only the newest piece of a much larger Amazon footprint in northern Indiana; the company has described its combined commitment to the state since 2024, across several counties, as somewhere between $26 billion and $33 billion depending on which announcement you count, with Jasper County alone put at roughly $11 billion including this campus.
What the county actually got in writing
Jasper County's council approved Project Rise back in June, five months before anyone picked up a shovel, and attached nine separate commitments to the vote. The incentive package includes a ten-year, 50% property tax abatement across three parcels totaling 870 acres. In exchange, AWS is paying $98 million in taxes upfront, with roughly $700 million more scheduled over the next 30 years. County officials project that Jasper County's data-center-related tax revenue, running at about $1.2 million a year before this deal, will climb past $420 million within 15 years. AWS also committed $25 million to extend public water service into Wheatfield Township, and a separate $1.25 billion pledge aimed at offsetting the impact its own electricity demand would otherwise have on everyone else's power bill.
Water use is capped at 24 million gallons a day for the broader Indiana Enterprise Center site. AWS says its own design, which relies on free-air cooling for roughly 98% of the year, should keep actual usage under 21 million gallons a day. None of that is a number from a press release. It's a condition the county can hold the company to, because the county is the one that voted on it and can revisit the vote if the company doesn't deliver.
The power behind it, and who's actually paying for it
The electricity for Project Rise didn't come from nowhere, and it came out of the same June regulatory window. Indiana's utility commission approved a special contract and power purchase agreement between NIPSCO, its generation affiliate, and Amazon Data Services, along with roughly 2.6 gigawatts of new gas-fired generation — two 1.3-gigawatt combined-cycle units — and a 400-megawatt, four-hour battery system. NiSource, NIPSCO's parent, says the costs of the generation and transmission built to serve this load fall on Amazon, not on NIPSCO's other ratepayers. That's the same structural protection this blog has flagged favorably in deals from Texas to Oregon: the company that needs the power pays to build it, rather than quietly spreading the bill.
It isn't a cost-free bargain for the area around it. The new gas plant sits about half a mile from NIPSCO's Schahfer coal-fired station, and one critic, cited in regional reporting on the project, has estimated the new units could emit close to four times what Schahfer's coal-fired generation put out in 2023. The Federal Energy Regulatory Commission still has to sign off on the power purchase agreement; I could not confirm that it has yet. And while the county's water cap reads as a serious number on paper, Circle of Blue has reported that a meaningful share of Jasper County residents outside the utility's service area still pull their own water from private wells drawing on a shallow local table — people whose supply isn't covered by anything in the county's 24-million-gallon ceiling, because they were never on NIPSCO's water system to begin with.
A real objection, not yet a large one
Local opposition exists, and it's worth naming honestly rather than either dismissing it or inflating it. A legal fund calling itself Protect Jasper County's Future Today has been raising money to challenge the NIPSCO gas plant specifically, citing pollution, water, and farmland concerns. As of the most recent snapshot I could find, it had raised a little over $1,490 toward a $10,000 goal. That's a genuine objection from genuine residents, and the well-water gap it points to is a real one: a water-use cap written into a county ordinance doesn't extend to a household down the road whose pump was never tied into NIPSCO's system in the first place, and nothing in the county's approval requires anyone to check on those wells before or after construction. It is not, so far, a mass movement capable of stopping or reshaping the project, and it would be dishonest to write it up as one.
The law the Statehouse couldn't hold the line on
Here's the part of this story that happened sixty miles away, at the Indiana Statehouse, in the same year Jasper County was negotiating its own deal. Lawmakers spent this year's session debating a rule that would let any Indiana locality collect a real, calculable payment from a data center hosted there: at least 1% of the facility's equipment purchases and electricity costs, as the Senate originally wrote it. By the time House Bill 1210 reached the governor's desk, after private negotiations between legislators and data-center industry lobbyists, that 1% of actual spending had been rewritten into a payment of not more than one cent on the dollar of value from the state's existing 7% sales-tax exemption — and any data center that already held an exemption certificate was excluded from paying even that. The bill's own lead sponsor, Rep. Craig Snow, told the Indiana Capital Chronicle the final version amounted to "really just not a lot."
The money already on the table makes that gap easy to measure. Indiana has forgone more than $825 million in sales-tax exemptions across 13 data center projects representing roughly $31 billion in investment, according to reporting in the Indianapolis Business Journal, and separate state figures count seven projects totaling $20.8 billion that have already qualified for the same exemption. Kasia Tarczynska, an analyst at the tax-incentive watchdog Good Jobs First, has argued that gap will only widen as more of the roughly 30 data center proposals reportedly working their way through Indiana's pipeline come up for approval, each one eligible for the same state exemption and now, at most, a fraction of a percent back to the community hosting it.
I think that contrast is the real story behind Thursday's shovels, more than the groundbreaking itself. A county council with actual veto power over the project got $798 million in direct payments, a water cap it can enforce, and a ratepayer-protection pledge, all in writing, before a single truck showed up. A state legislature trying to write the same kind of protection into a blanket law watched it shrink to a penny once the industry's lobbyists were in the room for the final draft. Jasper County had something the Statehouse didn't: a vote that was the one thing standing between Amazon and the site, with nowhere else for the company to go instead. Every other Indiana county watching this groundbreaking has that same power. The open question is how many of them keep it, once the next developer learns it's easier to go around a county council and lobby Indianapolis instead.