Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Louisville Gas & Electric (Kentucky), Rate EHLF Extremely High Load Factor Service
StatusApproved
Applies atContract capacity of 50 MVA or more (new customers only); expected average monthly load factor above 85% as in the sister KU tariff
Last reviewed2026-10-17
Contract term15 years
RampNot stated in the filings we read
Take-or-pay (minimum bill)80% of contract capacity billed monthly whether used or not
Collateral24 months of minimum bills
Exit feeRemaining minimum bills for the rest of the term
Notice to reduce or end60 months
Time to powerNot stated in the filings we read
SourceLG&E tariff P.S.C. Electric No. 14, Rate EHLF (psc.ky.gov/tariffs/electric/Louisville Gas and Electric Company/Tariff.pdf, read in full 2026-10-17); Kentucky PSC order in Case 2025-00114, February 16, 2026 (settlement summary read).

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site