Free tool

Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Arkansas Electric Cooperative Corporation (Arkansas), Transmission Extension of Facilities (TEOF) tariff
StatusApproved
Applies atPower Intensive Users: demand above 50 MW, single user or aggregated for the same entity in a member cooperative's territory
Last reviewed2026-10-14
Contract termNot stated in the filings we read
RampNot stated in the filings we read
Take-or-pay (minimum bill)Not stated in the filings we read
CollateralNot stated in the filings we read
Exit feeIf service is not taken for at least five years or the contracted term, the agreed contribution is still owed unless waived; if service never starts, 100% of costs incurred to that date
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourceArkansas PSC Order No. 6 in Docket 25-031-TF (read in full).

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site