Umatilla Electric Cooperative (Schedule 6, Large Industrial Rate
Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.
StatusApproved Last reviewed 2025-10-01
Applies atExpected or historical measured maximum demand over 10,000 kW (10 MW); also applies to any facility BPA designates, or plans to designate, a 'New Large Single Load'
What the filing saysRead in full from UEC's own Schedule 6 tariff (effective Oct 1, 2025, revised July 2025): 100% pass-through of wholesale power, transmission and BPA costs with no cooperative markup. Delivery Charge of $1.24 per kVA of Installed Capacity per month. A reactive-power-factor penalty applies if power factor falls below 97%. Financial security is required under the schedule's Exhibit A; an individual service agreement with UEC can supersede the schedule's default terms. Covers UEC's full territory across Umatilla, Morrow and Union Counties. Re-checked 2026-11-09 (UEC's own rates page, read directly): Schedule 6 is still listed at its Oct 1, 2025 effective date alongside every other UEC schedule except Schedule 11 (unrelated transmission service, 2022); no newer revision found.
Stated terms
This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.
Source
Umatilla Electric Cooperative, Rate Schedule 6 (umatillaelectric.com/wp-content/uploads/Rate-Schedule-2025-Schedule-6-FINAL.pdf), read in full; re-checked against umatillaelectric.com/rates 2026-11-09.
Compare with other utilitiesEstimate the commitment in dollarsCheck a site in Umatilla Electric Cooperative (Schedule 6 territory
Get an email when this changes
Other utilities in Oregon
Screening information from public filings, not legal or investment advice. Tariffs change; confirm the current terms with the utility and the commission before relying on them.