Brownsville Passed a Data Center Moratorium in November. SpaceX's $24 Billion Starbase Campus Was Already Outside City Limits.
SpaceX wants $74 billion for data centers in Texas and Arizona. The Texas land left city limits months before residents got a vote on pausing projects like it, and the Arizona site was filed under a different company's name.
On November 4th, Brownsville, Texas city commissioners passed a 90-day moratorium on new data center permits. Residents at that meeting had asked for twice that long, 180 days. It was a real response to a real fight that had been building in the city for months. It also didn't touch the project that was almost certainly driving it, because the land under that project had already stopped being part of Brownsville three months earlier.
How Starbase got outside the city's reach
In August, at SpaceX's request, Brownsville agreed to remove roughly 444 acres from its own city limits. The land didn't go back to the county unincorporated. It went to Starbase, the city SpaceX itself got incorporated in 2021 around its South Texas launch site, where two of the three sitting city commissioners are SpaceX employees. Starbase annexed the tract shortly after. In exchange for Brownsville's cooperation, SpaceX offered $220 million toward the city's water and wastewater systems, enough, by the company's own figures, to add 20 million gallons a day of capacity that Brownsville's utilities board will own outright, whatever happens to the data center next door. That's real money solving a real infrastructure problem a border city has wanted fixed for years, and I don't think it should be waved away as a bribe. It's also the reason that when residents pushed Brownsville into a moratorium on new data center permits this month, the city could only pause permits inside a city limit the project in question had already left.
Starbase's own commission takes the next step on December 9th, when it holds a public hearing on a property tax abatement for the $24 billion campus. The public notice doesn't disclose the abatement's size or length. The campus will run almost entirely on power it generates itself, through an on-site gas-fired plant built alongside the computing facilities, rather than drawing from the public grid. That design choice does more than one kind of work. It means the project doesn't need an ERCOT interconnection, so Governor Abbott's pause on new data center grid connections, issued in August pending a water and reliability audit, doesn't apply to it either. The plant still needs a Texas Commission on Environmental Quality air permit, where Abbott separately ordered a halt on data center permits, so that checkpoint, at least, remains open. Texas has been down this road before: the state's own survey of data center water use, the one that produced the Attorney General's $500-per-day fine threat against operators who wouldn't answer it, exists precisely because so much of this industry's resource footprint in Texas has been built outside the processes that would normally require an answer.
A $74 billion plan, announced the same week
The Starbase buildout is one piece of a $74 billion plan SpaceX announced November 12th, split between the Texas campus and a second, larger one roughly 1,300 miles away in Cochise County, Arizona, priced at about $50 billion. Combined, SpaceX says the two campuses will generate more than 6,000 construction jobs and more than 1,500 permanent ones; a separate figure specific to the Arizona site alone puts its construction jobs around 5,500, a number that doesn't cleanly reconcile with the combined total and that I'm flagging rather than picking one to use. Both projects are enormous by any standard that existed two years ago. The Arizona campus alone, at up to 6 gigawatts, would draw something close to what a mid-sized American city uses.
The same playbook, a different mechanism, in Arizona
Cochise County's own paperwork doesn't mention SpaceX at all. The special-use application for the 747-acre site near the Willcox Playa, filed with the county as SU26-22, lists the applicant as Tombstone Resources LLC. SpaceX confirmed to a local television station that it's the company behind the filing, and a representative said the SpaceX name was kept off the application because it "draws attention" from outside the county. If the goal was to keep the project quiet, it didn't work. Roughly 275 people turned out to a community meeting at Cochise Elementary School on November 5th, and a sizable share of them came holding "No Data Center" signs and talking over the company's own twenty-minute presentation almost as soon as it started.
The number nobody wrote down
The substance of the fight is water. SpaceX says the Arizona campus will use dry cooling, won't pump groundwater from the Willcox basin for industrial purposes, and will use roughly as much water as 20 to 30 ordinary households. Those are specific, falsifiable claims, which is more than most developers offer this early. What residents who actually read the application noticed is what isn't in it: no stated estimate, anywhere in the filing, of how much water a fully built, 6-gigawatt campus would need. "We don't know enough, therefore just say no," Michael Gregory told reporters at the meeting. Not everyone in the room agreed. "We need AI centers. It's the future," said Herald Satterlee, at the same meeting. A petition opposing the project has collected close to 2,200 signatures, and opponents have raised a second concern beyond water use: the Willcox Playa is a seasonal stopover for sandhill cranes, and nobody in this fight, on either side, has offered an environmental review of what a campus this size does to that habitat. SpaceX's stock fell as much as 6% the week the Arizona opposition story broke, before the company came back a week later with the full $74 billion announcement and a steadier market reaction.
On GridPermit's own evidence ladder, both projects sit at an unusual place: real money, real engineering, real timelines, and genuinely weak public proof on the two questions that matter most where each site actually sits. Texas answered the interconnection and zoning questions by routing around them, self-generating power and moving the land to a jurisdiction that wanted the deal. Arizona answered the water question with an assertion instead of a number, in an application that otherwise reads as detailed. Neither is necessarily wrong on the merits. A self-generating plant really does take pressure off a grid that Texas regulators themselves say is strained. Dry cooling really does use less water than evaporative systems. But a claim is not the same rung on the ladder as a number a county can hold a company to later, and right now, that's the rung both of these projects are missing.
Texas and Arizona are actually running the same annexation trick in opposite directions, which is worth sitting with for a second. Glendale, Arizona annexed 160 acres this fall specifically to gain the zoning authority it needed to approve a different data center, Project Eagle, on its own terms. Brownsville did the reverse: it gave up 444 acres specifically so the authority it would otherwise have had, the authority its own residents just tried to use, would belong to someone else. Annexation isn't a loophole by itself. It's a tool a city can use to grab jurisdiction or shed it, and which direction a given city points it in says more about who's asking than about the land itself.
December 9th is the date that forces the question in both places at once. Starbase's commissioners, two of whom work for SpaceX, decide whether to abate the Texas campus's taxes. Cochise County's planning commission decides whether to grant the special-use permit Arizona's campus needs to exist at all. Neither vote will settle whether $74 billion in AI infrastructure is good for the two places that will host it. Both will settle something narrower and more useful: whether the public bodies built to ask hard questions about water and power still get to ask them, once a company is large enough, and fast enough, to make sure it's asking somewhere else instead.
Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.