November 14, 2026 · Brendan Hogan, Founder, GridPermit

Wythe County, Virginia Has Never Had a Zoning Law. A $1 Billion Data Center Just Broke Ground There Anyway.

Wythe County gave the land away for free and has no zoning code at all. Construction just started on its first data center, while residents argue over whether it uses 2,000 gallons of water a day or far more.

Andy Kegley has spent most of this year doing something a lot of rural county officials never have to do: arguing that his own county needs a zoning code before it signs away any more land to data center developers. Kegley is a former Wythe County supervisor and now chairs a local group called Preserve Wythe. His complaint is specific and, as of this year, accurate. Wythe County, Virginia, population around 28,000 and tucked into the mountains along Interstate 81 near Wytheville, has never adopted a zoning ordinance of any kind. On November 10th, a crew showed up at Progress Park, an industrial site east of town, and started building anyway.

The project is Fluidstack's, a 99-acre AI data center campus on Lot 35 of Progress Park, and county officials have put the total investment at more than $1 billion once land, power infrastructure, hardware, and workforce costs are counted. The site's original developer, a company called Solis Arx, announced the project in December 2025; Fluidstack took it over sometime in 2026 and briefed the county board on the change in June. Construction is expected to run in phases through the end of 2027, with Appalachian Power supplying the power.

The money is real, and so is the giveaway

Start with the part of this story that is genuinely good news for a county that has been losing industry for decades. Wythe County gave Solis Arx the Progress Park site at no cost; the company is on the hook only for grading and site prep. A Mangum Economics study commissioned for the project projects more than $10 million a year in new local tax revenue starting in 2028, on top of whatever enterprise-zone incentives the site already qualifies for. Appalachian Power and county officials have both said the project won't push up electricity rates for anyone else in the county. None of that is spin. A county that gave away land for a shot at $1 billion in private investment and a locked-in tax base, without raising its own residents' power bills to get it, made a real trade and got something real back.

Jobs are where the numbers stop agreeing with each other. Fluidstack's own public affairs lead has cited roughly 1,000 construction jobs at peak and 75 full-time jobs once the campus is running. The county's own board minutes, from a June estoppel certification, instead describe 200 to 500 employees once the site is fully built out, a very different number than Fluidstack's public figure and one that isn't clearly reconciled with it anywhere in the public record. At a June 30th board meeting, critics called both sets of numbers a myth, on the reasonable grounds that none of them appears in anything the county could actually hold the company to if the final campus turns out smaller, or more automated, than advertised. That's not a developer lying. It's a developer describing a plan that hasn't fully taken shape yet, in a county that has no mechanism to turn an estimate into a commitment.

A county with no rulebook, writing one now

Virginia has 95 counties, and by one count given to the Wythe County board, 87 and a half of them already have some form of zoning; Franklin County is the half, with a partial code. Wythe was one of the last holdouts, and local coverage has been direct about what that meant for this particular deal: the county's lack of zoning is exactly what let the Progress Park plan move as fast as it did, since there was no zoning board, no use-permit hearing, and no density or setback rule standing between a landowner and a data center. A county with no zoning code isn't a county that forbids industrial use. It's a county where almost nothing is forbidden, by zoning, anywhere.

In December 2025, the Board of Supervisors approved something that looks, on paper, like a step toward more structure: a new "Technology" zoning district, meant to give data centers a defined category instead of leaving them to fall through the cracks of a code that never anticipated them. The Piedmont Environmental Council, a regional conservation group that has tracked the county's process closely, reads that new category differently. Its concern is that the Technology district is written broadly enough to let almost any parcel in the county, not just land inside Progress Park, be rezoned for a data center campus if a future board votes to allow it. County officials haven't disputed that the category is broad. Their answer has been that any future rezoning under it would still require its own public hearing and its own board vote, which is true, and also beside the point Kegley and others are raising: a county that adopts a wide-open category can narrow it in practice only if every future board keeps choosing to.

Only after that backlash did Wythe County start drafting something it has never had: a general zoning ordinance covering the whole county, not just a single data center carve-out. The board held its first public input session on a draft code in the spring and ran a public comment period into September. If it passes, Wythe County will end up with its first countywide zoning ordinance in its history, written specifically because one project got built under a code that didn't exist yet to regulate it.

What nobody has agreed on is the water number

Water is the other number nobody has nailed down. County officials and the company have cited a projected 2,000 gallons of water a day for the campus's closed-loop cooling system, a figure one county presentation framed as just 0.13% of Progress Park's existing water capacity, which sounds reassuring until you notice it's a rounding error against a system most residents have no reason to know the total size of. Other meeting coverage has put the daily figure closer to 2,800 gallons. At a June 30th board meeting, a solutions architect who had reviewed the underlying numbers told supervisors that, depending on how large the finished campus ends up, actual water use could range anywhere from a few thousand gallons a day to hundreds of thousands. That's a real, wide, unresolved range, not a rounding dispute, and it's the kind of gap a closed-loop claim is supposed to close before a county relies on it, not after.

None of this has gone unnoticed locally. Fluidstack held an open house on October 29th to walk residents through the project under construction; protesters showed up anyway, frustrated that a public information session was happening after the land was already cleared rather than before. Not every county official has treated the two Wythe County data center proposals the same way, which is itself worth noting. One supervisor, Mr. Cook, has said he supports the Progress Park project specifically because the site was always designated for industrial use, while publicly opposing a separate, unsolicited proposal for roughly 1,000 acres near Exit 86 that was never zoned, planned, or set aside for anything like this. A third project, from TAC Data Centers, is moving forward in the eastern part of the county near the Pulaski County line, with that developer separately citing 150 to 200 permanent jobs. Wythe County isn't getting one data center decision. It's getting a pattern, in real time, of which sites a supervisor thinks a county with no zoning code should say yes to and which ones it shouldn't.

The useful way to read Wythe County right now isn't as a county that got fooled, or one that got rich. It's a county that discovered, in the space of about a year, exactly how much a zoning code is actually for. Progress Park moved from announcement to broken ground in under twelve months because nothing in county law required it to move slower. The ordinance Wythe County is writing now, its first ever, will govern every data center proposal that comes after this one. It will have had no say at all over the one that's already under construction.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report