November 17, 2026 · Brendan Hogan, Founder, GridPermit

The Krafts Want to Put a $16 Billion Data Center in a Town of 9,000. The State's New Rule Means the Kraft Group, Not Sutton's Ratepayers, Covers the Power.

Sutton, Massachusetts could collect $28 million a year from the Kraft Group's data center. Every resident who spoke at the first hearing opposed it, and no tenant has been named yet.

Sutton, Massachusetts has about 9,000 residents, one town hall, and as of this month, a proposal in front of its Select Board for one of the largest data center campuses in the country. The developer is the Kraft Group -- the family that owns the New England Patriots -- partnered with a company called Unified Global Packaging Group. The number attached to it is more than $16 billion. The scope: up to 10 buildings and roughly 900 megawatts of electricity at full build-out, on a 67 Unified Parkway site off Boston and Providence roads where the Kraft Group already runs packaging operations. If it's built as proposed, Boston Globe reporting puts it among the four largest data centers in the country, and its 900-megawatt draw at roughly 7% of what the entire state of Massachusetts used on last year's hottest summer day.

Town Manager Austin Cyganiewicz laid out what Sutton stands to gain in a memo to the Select Board: close to $28 million a year in property tax revenue. That's a real number for a town whose budget has been strained for years, the kind of money that rebuilds a fire station or holds the line on a tax rate without a town meeting fight. The Kraft Group has called the project "an opportunity to bring meaningful long-term economic investment to Sutton." Nobody from the company showed up to say so in person.

Every resident who spoke, spoke against it

At the Select Board's November 10th meeting, the room was full and the opposition was not close to split. One resident said the town shouldn't become, in effect, a dumping ground for the AI industry. Another described her position as staunch opposition to any data center plan in Sutton. Select Board Chair Jonathan Anderson said the board would not rush to a vote and would hold multiple public meetings with residents before anything moves forward. Board member Jesse Limanek, who lives six houses from the proposed site, said that if the town does write a bylaw allowing data centers, it needs real protections for the neighbors built into it, not just a revenue line for the town's books.

The gaps in what's public so far are real, not nitpicking. No tenant has been named -- this is a speculative campus, not a signed lease, which matters for exactly the reason this blog keeps coming back to: a company has every incentive to describe its own project in the best light before anyone outside it has verified a single number against a filing. No water-use figures have been released either, and water is usually the second fight after power in a project this size. Sutton's current zoning bylaws don't have a category for data centers at all, which means the Kraft Group can't just pull a permit. The town has to write new zoning through its own town meeting process first, a public, votable step, not an administrative sign-off.

The rule that changes who pays

Here's what makes Sutton worth writing about now rather than filing away as one more town fighting one more data center: Governor Maura Healey signed Executive Order 658 on September 8th, and it applies directly to this project. Any data center built or expanded after that date with more than 25 megawatts of peak demand needs local approval before it can get a state permit, and that local approval has to come with a community benefits agreement and a real plan for the project's water and energy impact. On the power side, the order requires the developer to either procure new clean generation equal to its own annual electricity use or pay into a ratepayer protection fund instead of passing that cost to everyone else's bill -- and it directs state utility regulators to make large speculative projects post deposits so they can't tie up a grid connection without serious intent to build. That's the same cost-causation principle GridPermit tracks in large-load tariffs from Oregon to Indiana: the entity that needs the power pays to build it, not the ratepayer next door who never asked for a neighbor this size.

The order didn't come out of nowhere. Healey's administration had already floated a softer version in June, a policy it called "Bring Your Own Clean Energy," asking data center developers to voluntarily match their own power draw with new clean generation. September's order made that mandatory and tied it directly to the permitting process instead of leaving it as a request a developer could politely decline. Massachusetts also isn't the only place testing this right now: Westfield, in the western part of the state, has its own data center proposal working through the same post-order process, with developers there seeking a special tax assessment for a payment-in-lieu-of-taxes arrangement with the city -- a different financial structure than anything on the table in Sutton so far, but the same underlying question of what a town gets in exchange for hosting the load.

Healey signed that order with utility bills already a central issue in her own re-election campaign, and it was written broadly enough to function, in practice, as a pause on new data center approvals in Massachusetts until a town says yes first. Sutton is the live test of what that actually means when the company asking is one of the most recognizable names in the state and the number is $16 billion. A community benefits agreement and a zoning bylaw are not small asks, and nothing requires Sutton's town meeting to approve either one.

There's also a harder deadline buried in the mechanics of the order that doesn't get much attention next to the headline dollar figures: the DPU's deposit requirement for speculative projects above 25 megawatts. That provision exists because utilities across the country, not just in Massachusetts, have spent the past two years fielding interconnection requests from developers who never had a real site, a real tenant, or real financing lined up -- requests that clog a queue everyone else then has to wait behind. Whatever else Sutton's residents and the Kraft Group disagree about, the project at least clears that lower bar: a named site, a named developer with its own balance sheet, and a town manager's memo with a real tax-revenue estimate attached. That's more than a lot of the proposals this rule was written to filter out ever had.

I think the real question in Sutton isn't whether $28 million a year is worth it -- that's a number the town will argue about for months, and it should. The more interesting question is whether Healey's order does what it's designed to do: force the actual negotiation over water, power, noise, and who bears the cost to happen in public, on the town's own calendar, before a shovel goes in the ground, instead of after. Every data center fight this blog has covered that went badly did so because that negotiation happened too late, or not at all. Sutton gets to have it first. What the town does with that leverage is still an open question, and right now, the only answer on the record is a room full of residents who want none of it.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report