November 19, 2026 · Brendan Hogan, Founder, GridPermit

Boise Banned Mega Data Centers Before a Single One Applied. The 4-Million-Square-Foot Project That Prompted It Sits Outside the Ban's Reach.

Boise's council voted unanimously, in four days, to block data centers that don't exist yet. The 4-million-square-foot one actually in motion sits on federal land the ban can't touch.

Boise Mayor Lauren McLean didn't wait for a data center to show up before going after one. On Friday, November 6th, she proposed an emergency six-month ban on large data centers inside city limits. By Tuesday, November 10th, the city council had passed it, unanimously, and it took effect the moment the vote closed. No company has an application pending anywhere in Boise. McLean said that was the point. "I'm doing this now before we have an application so that we can be sure that we get it right," she told reporters.

A ban with nothing yet to ban

The ordinance leans on a provision in Idaho code that lets a city act immediately, without the usual notice period, when it finds "imminent peril to the public health, safety, and welfare." It bars the city from accepting or processing any application for a data center of 100,000 square feet or more, or one drawing 20 megawatts of power -- including power the facility would generate on site -- whichever threshold a project hits first. Data centers already operating in Boise, permitted before the ordinance existed, are untouched. More than 100 people showed up to the hearing before the vote. Reporting from the meeting is consistent on one point: nobody stood up to defend data centers or asked the council to slow down. Several residents asked the council to go further -- one wanted a threshold of zero square feet, zero megawatts, a ban in name and in fact.

McLean's own framing of the ordinance was blunter than most mayors get on the record about a type of project their own state is actively courting. "These mega data centers don't belong anywhere in Idaho, and in the absence of a state-wide moratorium, I'm pulling the emergency brake to protect Boiseans and our precious natural resources," she said in the statement announcing it. The six months buys the city time to rewrite its own code: new definitions, new standards, and a real look at water use, electricity demand, wastewater, noise, and public safety before the next proposal arrives, not after. If that isn't enough time, the city can follow with a longer interim ordinance covering up to twelve more months.

The project the ban can't touch

Here's the part that makes Boise's pause more interesting than a standard not-in-my-backyard moratorium: the project that actually prompted it sits outside the city's jurisdiction entirely. Rhea Data, a subsidiary of the Nevada-based developer Arevia Power, has proposed a roughly 4-million-square-foot data center campus on somewhere between 3,200 and 3,700 acres of federal land managed by the Bureau of Land Management, near Blacks Creek Reservoir, about four miles southeast of Boise's city limits, close to Interstate 84. The plan includes an on-site natural gas plant to help cover the campus's own power demand. Because the land is federal and the site sits outside Boise proper, nothing in the city's emergency ordinance reaches it. A unanimous vote, an immediate effective date, and a mayor's public emergency-brake rhetoric all stop at a line on a map that Rhea Data's chosen site happens to sit just past.

The federal review that actually governs the Rhea Data site is still barely underway. The BLM has described its own process as being in a "pre-planning phase" and says it is still waiting on basic information from the company, including how much water the campus would need and what cooling method it would use -- the same water-demand figure that, time and again on this blog, turns out to be the detail a company is slowest to put in writing. One tracker following federal data center proposals expects the BLM to publish a formal notice of intent, the document that starts the clock on environmental review under NEPA, sometime before the end of this year. Until then, there is no public water number, no finalized acreage, and no approved project -- just a filing working its way through a federal agency on a timeline the city of Boise has no vote in.

McLean had already weighed in on that gap before she ever proposed the moratorium. In September, when the Rhea Data proposal first became public, she issued a statement calling the idea of selling off public land for mega data centers "shortsighted" -- an argument about who gets to decide what happens to land near a reservoir and a bird habitat that the city of Boise doesn't own and can't zone. Idaho's Sierra Club chapter made a similar case more pointedly. Chapter director Lisa Young called the proposal "unacceptable," and communications coordinator Vienne Aberle argued that the land near Blacks Creek exists for wildlife, clean water, and recreation, not a server farm with its own gas plant. The site sits just south of the Blacks Creek Bird Reserve, and other conservation groups tracking the area's big-game migration corridors and its fishery have raised related concerns of their own.

The gap that actually matters here

Boise isn't the only Idaho jurisdiction reaching for a pause this year. Bannock County, in the eastern part of the state, adopted its own 180-day data center moratorium back in July, months before Boise's. McLean has said plainly that she would rather Idaho pass a statewide rule than leave this to each city and county to improvise on its own timeline, which is exactly the problem a patchwork of local moratoriums can't solve: a six-month pause only binds the government that passed it.

I think that's the real story underneath Tuesday's unanimous vote, more than whether Boise is for or against AI infrastructure. A city council can move fast when it wants to -- four days from proposal to passage, effective on the spot, aimed at a threat that doesn't technically exist inside city limits yet. What it can't do is reach past its own boundary to the one project that's actually furthest along. Rhea Data's campus is working through a federal agency's pre-planning process, on federal land, answerable to federal environmental law, with a water figure nobody outside the company has seen yet. Boise just proved how much authority a city actually has over a data center it hasn't met. The harder question, for Boise and for every county watching this fight, is how much authority anyone has over the one that's four miles away and moving.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report