Arkansas Regulators Rejected This Solar Deal in September. One Month Later, Google and Entergy Filed It Again, With a $500 Million Pledge Attached.
Arkansas rejected this 440-megawatt solar contract for unproven costs in September. A month later Google and Entergy refiled it, wrapped in $600 million of grid upgrades and a promise that it saves everyone else $500 million.
West Memphis, Arkansas got a new neighbor last year: Google's $4 billion data center campus, the kind of project that turns a county utility's filings into the most contested paperwork in the state. Powering it has already cost Entergy Arkansas one federal lawsuit and one commission rejection. Now it's trying a second time for the exact deal that rejection stopped. On October 19th, exactly one month after the Arkansas Public Service Commission said no to a 440-megawatt solar contract tied partly to Google's growing appetite for power, Entergy and Google were back in front of the same commission with the same project, this time folded into a bigger filing carrying a bigger number: $600 million in new grid infrastructure, and a promise that every other Entergy Arkansas customer comes out $500 million ahead for it.
The deal that didn't survive the first time
The project in question is Big Island Solar, a 440-megawatt facility in Mississippi County that Entergy signed up through a 20-year power purchase agreement in December 2025 and asked regulators to approve the following month. The pitch was straightforward: new generation to meet growing demand, including Google's West Memphis campus. On September 19th, the commission said no in a 52-page order that read less like a close call than a checklist of unmet burdens. Entergy hadn't shown the contract's costs were reasonable, hadn't proven it beat the alternatives state law requires a utility to weigh before signing a 20-year commitment, and had leaned on renewable energy credit revenue that was still being negotiated with Google at the time the company asked regulators to sign off anyway. The commission also questioned whether Entergy had demonstrated a genuine need for the capacity at all. Four separate, specific failures, not one technicality -- the kind of order that exists to be taken seriously the next time the same pitch shows up.
What's actually new this time
What showed up a month later is bigger, not smaller. Entergy's October 19th filing wraps the Big Island capacity into a broader second-phase package for the West Memphis campus: roughly $600 million in grid infrastructure that Google agrees to fund directly, including an expanded substation and new transmission lines, plus two battery storage systems near Osceola and Hot Springs totaling about 1,400 megawatt-hours, both targeted to be operating by 2028. A separate solar component, tied to the Steel River project in northeast Arkansas and built with Cypress Creek Energy, adds further capacity to the grid rather than serving Google's load exclusively. None of it goes into service, or into anyone's rate base, until the same commission that rejected Big Island in September signs off on this version.
The case for calling this a real win isn't just the dollar figure. Grid infrastructure -- substations, transmission lines, batteries sited in two specific towns -- is harder to walk away from than a press release, and it serves more than one customer once it's built. That distinguishes it from a pure power purchase contract, where the only thing anyone can verify before construction starts is a signature. Entergy is also leaning on that distinction explicitly. Laura Landreaux, the utility's president and CEO, described the filing as reflecting "thoughtful planning, responsible investments, strong regulatory oversight and customer protections," and said Google is building on the success of the first phase rather than starting something new. On top of the $1.6 billion in savings Entergy already pledged under its company-wide "Fair Share Plus" commitment, the utility says this package delivers at least $500 million more for its roughly 760,000 other Arkansas customers over the next 20 years, starting in 2028.
The number nobody outside Entergy can check yet
Here's where the September order should matter again. Trade publications covering the October filing have already flagged that Entergy's release doesn't explain how the $500 million savings figure was calculated, and gives no total for what Google ultimately pays over the life of the deal. That's not a new complaint about this company. When public records obtained by the Arkansas Democrat-Gazette in September revealed what Google was actually paying toward Entergy's separate, already-approved Cypress Solar project, Entergy's response wasn't just a press statement disputing the paper's math -- it asked a federal judge for a restraining order to block two Arkansas news outlets from publishing the underlying figures at all, arguing some of the material was a trade secret. U.S. District Judge Lee Rudofsky denied that request the same day, treating it as functionally a request for prior restraint on the press. Entergy dropped the whole lawsuit two weeks later without pursuing damages. Arkansas's legislative Joint Energy Committee has since questioned both companies directly about who actually carries the cost when a hyperscaler's power needs outgrow the generation built to serve it, and the co-chair publicly criticized Entergy's decision to sue the newspaper in the first place.
None of that means the $500 million pledge is false. It means the only people positioned to check it are the same commissioners who spent most of this year checking Entergy's other numbers and finding real gaps in some of them. That's the system working the way it's supposed to, not a reason to assume bad faith -- Arkansas's commission already proved in September it will say no to a Google-adjacent deal when the math doesn't hold up, which is exactly the leverage ratepayers need an advocate to use again here.
There's no public docket schedule yet for how long this review takes. Entergy's own timeline has the grid work entering service in 2028, which leaves roughly two years for the commission, its staff, and Arkansas's attorney general to go through the same exercise they ran on Big Island the first time: check whether the savings math holds, whether the capacity is actually needed, and whether the REC and demand assumptions underneath the number are locked in or still being negotiated with Google behind the scenes. Nothing about refiling a rejected deal inside a bigger package changes what the statute requires a utility to prove before regulators sign off on a 20-year commitment.
I think the useful question isn't whether $500 million sounds believable in a press release. It's whether the commission that wrote a 52-page order four distinct findings deep in September holds the refiled version of the same project to that same bar, or treats a bigger number wrapped in more infrastructure as reason enough to wave it through. The evidence ladder this blog keeps coming back to runs on exactly that distinction: a dollar a company has already spent sits in a different place than a dollar it's promising to spend, no matter how many zeros are attached or how much grid infrastructure gets named in the same filing. Arkansas already showed this year it knows how to tell the difference. The refiled Big Island deal is the chance to find out whether that was a one-time exception or a standing rule -- and whether $600 million in substations and batteries is enough to change which one it turns out to be.