Google Turned Down a 20-Year Tax Break in Rural Kansas. Six Weeks Later, It Still Hasn't Signed the Deal.
Barber County, Kansas, population 4,000, talked Google out of a tax exemption and into $320 million over 20 years. The county's own paperwork still says the deal isn't signed.
Barber County, Kansas, has about 4,000 people, a county seat (Medicine Lodge) of fewer than 1,800, and a median household income under $46,000. On August 31st, its three-member commission called a special meeting to finish a deal nobody that small usually gets asked to sign: three agreements with Google for a 1.7-million-square-foot data center outside the town of Sharon. The room was full. People wanted to know what the county was agreeing to before anyone signed anything.
What the commission approved, on a 2-0 vote with one member abstaining, is Project Helium, Google's first data center in Kansas, built on farmland about eight miles east of Medicine Lodge. Google says the campus will eventually run "thousands" of servers and support up to 500 permanent jobs, with earthwork expected to start around 2027 and the first building operating by 2030. For a county this size, that's not an incremental project. It's close to the only industrial development most of Barber County has ever had, or will have.
What makes the deal unusual isn't the size. It's the tax bill. Kansas law lets counties grant data centers of this scale up to 20 years of property tax exemption, the standard play nearly every state uses to compete for these projects. Barber County didn't take it. Under the agreement, Google pays the full amount of applicable property taxes, no abatement at all. Commissioner Bryan Quick put the number on the record: "Google will pay north of $320 million in taxes over the next 20 years." The county's own projection breaks that down as roughly $138.4 million to Barber County itself, with the rest going to the school district and other local taxing bodies over the same 20-year term.
Why saying no to the tax break is the real story
Quick's other quote explains the thinking better than the dollar figure does: "We thought it was in our best interest to get some type of agreement with Google now, so we didn't end up not having one." That's not a ringing endorsement. It's a county that watched what these deals look like elsewhere and decided a sure thing beat a better-sounding one. This blog has already covered the alternative: Kokomo, Indiana, where the mayor turned down an abatement on the same logic and landed a $1.3 billion Digital Realty campus anyway. Barber County is now the second place in two weeks to bet that a developer with real money behind it doesn't need a tax break to show up, and that an exemption, once granted, never comes back.
Google also agreed to pay the county $5.5 million directly in community benefit payments, meant to cover costs the county takes on just from having a construction project this size land on its roads and in its budget before any tax revenue starts flowing. The first installment, $500,000, is due by the end of this year. For a county whose entire annual budget doesn't come close to that figure, having real money up front, before a single server runs, is the part that's genuinely hard to find fault with.
The environmental terms are more specific than most data center deals bother to be. The facility is closed-loop and air-cooled, not water-cooled, and the development agreement states plainly that "Google shall not drill or construct any new water well on the property." The one existing well on site can be used for domestic purposes only; everything else the facility needs has to come from the regulated municipal utility, with wastewater handled the same way. The site also has to sit more than 2,000 feet from the nearest homes and the Sharon city limits, with separate daytime and nighttime noise limits. In a part of the country where a bad water story usually ends up defining a data center project, this one got ahead of that fight before it had a chance to start.
What the county still can't confirm
None of that answers the question that was actually in the room on August 31st. The commission's vote wasn't unanimous support. It was two yes votes and one abstention, and the meeting that finalized everything was called on short notice. Coverage in the weeks after described residents showing up to later meetings still asking for more transparency, wanting to see the actual terms rather than a press release summarizing them.
Here's the part that should bother anyone trying to track this deal from the outside. More than two weeks after the vote, the county's own "deal summary" document still described the terms as "subject to final approval and execution by both parties." A local television station later reported that the county attorney confirmed Google had not yet signed the agreement. A commission can vote to approve a deal and put out a press release announcing it the same day. Whether that deal is actually binding is a separate fact, with its own separate paper trail, and in Barber County's case that paper trail was still open six weeks after the vote made headlines.
That gap is exactly the kind of thing GridPermit's own diligence work is built to catch. A commission's 2-0 vote and a press release are real, but they sit on a lower rung of the evidence ladder than an executed agreement with both signatures on it. The Kill Test exists for the same reason this county's own hedge language does: a project can be announced, approved, and covered by every outlet in the state, and still not exist on paper yet, and the gap between those two things is exactly where a diligence process either catches something or misses it.
Barber County came out of this with a better deal than most places get: full taxes, real money up front, a water policy that heads off the fight before it starts. What it doesn't have yet, as of this week, is Google's signature on the paper that makes any of it enforceable. Four thousand people have a commission that promised them a deal. The deal itself is still, on the record, unfinished.
Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.
Start a Qualification ReviewSee state-by-state coverage · Read the methodology · See a sample report