Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

We Energies (Very Large Customer tariff)
StatusApproved
Applies at100 MW or more of energy demand
Last reviewed2026-04-24
Contract termMinimum initial term of 15 years (PSC decision of April 24, 2026)
RampNot stated in the filings we read
Take-or-pay (minimum bill)Not stated in the filings we read
CollateralNot stated in the filings we read
Exit feeNot stated in the filings we read
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourceWisconsin PSC press release, April 24 2026: https://psc.wi.gov/Documents/PressReleases/04.24.2026PressRelease.PDF

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site