Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Rappahannock Electric Cooperative (Virginia), Schedule LP-DF Large Power and Dedicated Facilities
StatusApproved
Applies atContracted billing demand above 25 MW, served at 34.5 kV or higher from dedicated substation facilities, at an annual average load factor of at least 75%
Last reviewed2026-10-14
Contract termNegotiable but structured to recover the full cost of distribution and sub-transmission plant; the length is in the agreement, not the schedule
RampNot stated in the filings we read
Take-or-pay (minimum bill)Not stated in the filings we read
CollateralCredit collateral support set by the cooperative; amounts are in the agreement, not the schedule
Exit feeNot stated in the filings we read
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourceRappahannock Electric Cooperative Schedule LP-DF, effective 4/15/2026 (myrec.coop, read).

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site