Compare large-load tariffs side by side
Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.
Comparison
| Portland General Electric (Schedule 96; large load agreements under Rule I) | |
|---|---|
| Status | Approved |
| Applies at | 20 MW or more for a large load customer agreement (LLCA); Schedule 96 applies to large energy use facilities of 20 MW or more |
| Last reviewed | 2026-05-07 |
| Contract term | Minimum 10 years at 20 MW, plus one year per 10 MW increment, up to 30 years at 220 MW or more (Order 26-154) |
| Ramp | Not stated in the filings we read |
| Take-or-pay (minimum bill) | Not stated in the filings we read |
| Collateral | Not stated in the filings we read |
| Exit fee | Not stated in the filings we read |
| Notice to reduce or end | Not stated in the filings we read |
| Time to power | Not stated in the filings we read |
| Source | Oregon PUC Order No. 26-154, Docket UM 2377 (May 7 2026): https://apps.puc.state.or.us/orders/2026ords/26-154.pdf; Gov. Kotek state-land pause, announced Sept 8 2026 (news coverage: kptv.com, datacenterdynamics.com, wweek.com; Governor's office primary text not directly located during this research). |
Shaded rows differ between the utilities. Faded values are not stated in the filings we read.
Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site