Free tool

Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Madison Gas and Electric (Wisconsin)
StatusPending
Applies atNot confirmed (the filing was not read; Xcel Wisconsin proposed about 100 MW and the We Energies decision set 100 MW)
Last reviewed2026-10-14
Contract termNot in structured terms yet; see the source
RampNot in structured terms yet; see the source
Take-or-pay (minimum bill)Not in structured terms yet; see the source
CollateralNot in structured terms yet; see the source
Exit feeNot in structured terms yet; see the source
Notice to reduce or endNot in structured terms yet; see the source
Time to powerNot in structured terms yet; see the source
SourceEEI list, Sept 2026 (docket numbers); newprojectmedia.com coverage of the Xcel filing; Data Center Knowledge on the We Energies decision. Dockets not read.

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site