Free tool

Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Liberty (Empire District Electric), Missouri large load tariff case
StatusPending
Applies at25 MW or more of new or expanded load (Schedule TS-LL, as filed); Liberty may aggregate nearby premises
Last reviewed2026-10-14
Contract termFixed term of at least 15 years, then automatic 5-year extensions (Schedule TS-LL as filed)
RampOptional load ramp of up to 5 years
Take-or-pay (minimum bill)Not stated in the filings we read
CollateralNot stated in the filings we read
Exit feeNot stated in the filings we read
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourceLiberty direct testimony of Charlotte Emery with the Schedule TS-LL term summary, ET-2026-0184 (efis.psc.mo.gov, read); Missouri PSC large-load fact sheet, April 2026 (read).

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site