Compare large-load tariffs side by side
Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.
Comparison
| Imperial Irrigation District (California), Schedule LL Large Load | |
|---|---|
| Status | Approved |
| Applies at | Expected monthly demand of 20 MW or more and an expected load factor above 80% |
| Last reviewed | 2026-10-14 |
| Contract term | Initial contract term of at least 15 years, set in the Electric Service Agreement, then continuing until ended |
| Ramp | Not stated in the filings we read |
| Take-or-pay (minimum bill) | Not stated in the filings we read |
| Collateral | Service deposit of at least 3 months of demand and minimum charges, normally in cash, plus other collateral the agreement requires |
| Exit fee | Remaining Minimum Charge for any terminated or reduced capacity for the rest of the initial term |
| Notice to reduce or end | At least 60 months' written notice to end or change service |
| Time to power | Not stated in the filings we read |
| Source | IID Schedule LL tariff PDF and Large Load Customers page (iid.com, read). |