Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Evergy Kansas Central / Evergy Kansas South (Schedule LLPS)
StatusApproved
Applies atMonthly maximum demand of 75 MW or more for a new facility, or an expansion of 75 MW or more
Last reviewed2025-11-06
Contract term12 years after the ramp
RampUp to 5 years
Take-or-pay (minimum bill)80% of contract capacity billed monthly whether used or not
CollateralNot stated in the filings we read
Exit feeNot stated in the filings we read
Notice to reduce or endNot stated in the filings we read
Time to powerNot stated in the filings we read
SourceEvergy Kansas Central Schedule LLPS, KCC docket 25-EKME-315-TAR (approved Nov 6 2025): https://www.evergy.com/-/media/documents/billing/kansas-central/commercial-and-industrial/ekc_large-load-power-service.pdf