Free tool

Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Duke Energy Florida, proposed Large Load Customer Policy (Florida PSC)
StatusPending
Applies at50 MW or more of firm load (Peak Contract Demand reasonably expected at or above 50,000 kW at any time in the term)
Last reviewed2026-10-14
Contract term20 years (includes the ramp)
RampNot stated in the filings we read
Take-or-pay (minimum bill)80% of contract capacity billed monthly whether used or not
CollateralNot stated in the filings we read
Exit fee3 years of minimum bills
Notice to reduce or end24 months
Time to powerNot stated in the filings we read
SourceDuke Energy Florida petition and proposed tariff sheets, Docket 20260064-EI, filed April 22, 2026 (floridapsc.com, read); contest from reporting on the docket, not read.

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site