Compare large-load tariffs side by side

Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.

Comparison

Consumers Energy (Rate GPD large-load / data center provision)
StatusApproved
Applies at100 MW or greater; or an aggregate of 100 MW under common ownership where each site is 20 MW or more
Last reviewed2025-11-06
Contract term15 years after the ramp
RampUp to 5 years
Take-or-pay (minimum bill)80% of contract capacity billed monthly whether used or not
CollateralNot stated in the filings we read
Exit feeRemaining minimum bills for the rest of the term
Notice to reduce or end48 months
Time to powerNot stated in the filings we read
SourceMPSC order, Case No. U-21859 (issued Nov 6, 2025, 129 pages, read in full): https://adms.apps.lara.state.mi.us/Mpsc/ViewCommissionOrderDocument/27293

Shaded rows differ between the utilities. Faded values are not stated in the filings we read.

Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site