Free tool
Compare large-load tariffs side by side
Pick up to three utilities. See status, the contract term, the minimum bill, collateral and exit fee each filing states, with the source. Add a size and a demand charge to see what the minimum costs in dollars.
Comparison
| Appalachian Power Company (Virginia), Schedule L.P.S. large load terms | |
|---|---|
| Status | Approved |
| Applies at | 100 MW or more at an individual site, or 150 MW or more aggregated (new load or expansion after July 1, 2025) |
| Last reviewed | 2026-10-14 |
| Contract term | 14 years (includes the ramp) |
| Ramp | Up to 4 years |
| Take-or-pay (minimum bill) | 80% of contract capacity billed monthly whether used or not |
| Collateral | Not stated in the filings we read |
| Exit fee | Not stated in the filings we read |
| Notice to reduce or end | 42 months |
| Time to power | Not stated in the filings we read |
| Source | Virginia SCC Final Order, Case No. PUR-2025-00057, June 1, 2026 (scc.virginia.gov, read in full). Stipulation Attachment 1 and compliance tariff sheets not read. |
Shaded rows differ between the utilities. Faded values are not stated in the filings we read.
Screening information from public filings, not legal or investment advice. The utility's signed agreement controls. See all coverage · Commitment estimator · Check a site