Dominion Energy South Carolina, large-load rules (generic PSC docket 2026-138-E)

Large-load tariff for data centers: what is on file, the terms the filings state, and where each fact comes from. Terms a filing does not state are marked, never guessed.

StatusPending  Last reviewed 2026-10-14
Applies atNot set. An advocacy filing in the generic docket refers to 25 MW or more of measured or contracted demand, but it is not adopted.
What the filing saysPENDING. In Dominion Energy South Carolina's rate case the PSC (Order 2026-374, July 2, 2026) approved a large-load stipulation under which Dominion joins the generic large-load docket 2026-138-E, still open in mid-2026 with no final tariff. No South Carolina minimum term, minimum bill, collateral or exit fee is published yet. Parties are arguing that any tariff must include minimum bills, exit fees, collateral and contract timelines. The stipulation terms were not read.

Stated terms

This tariff does not yet have terms we can tabulate. The status text above is what the filings and our source state. See the source below.

Source

South Carolina PSC filings in Dockets 2026-138-E and 2025-325-E located by search (dms.psc.sc.gov); summary only, filings not read.