October 17, 2026 · Brendan Hogan, Founder, GridPermit

Kelly Scott's Cattle Farm Sits 650 Yards From Wisconsin's Next Gas Plant. The Commission Approved It Anyway.

Wisconsin approved two billion-dollar gas plants for Microsoft and Oracle's data centers over 82-88% hearing opposition, with a signed Microsoft contract still carrying language regulators already ordered removed.

Kelly Scott's cattle farm sits on five acres in the Town of Darien, Wisconsin, land that's been in her husband's family for generations. The footprint of a proposed natural gas plant, 324 megawatts, comes to within about 650 yards of her front door. When the Public Service Commission held its hearing on the project this summer, Scott showed up and said so. She wasn't the only one who did. By several local accounts, every Darien resident who approached the microphone that night spoke against the plant. On October 15th, the commission approved it anyway.

It wasn't a one-off. The same day, in the same meeting, Wisconsin regulators granted conditional certificates of public convenience and necessity to two separate gas plants proposed by the Chicago-based developer Invenergy: Foundry Ridge, the 324-megawatt plant near Scott's farm, and Red Oak Ridge, a far larger project 45 miles away in the Town of Paris, Kenosha County, reported at anywhere from 1,120 to 1,186 megawatts depending on the filing. Together, the two projects carry a price tag north of $2.2 billion. It is the first time in Wisconsin that a merchant developer, building power for sale rather than a utility building for its own ratepayers, has asked the commission for permission to build natural gas generation at this scale. State air permits from the Department of Natural Resources are still pending on both.

How much power do we need in Walworth County?Brian Conley, Darien resident, at the PSC hearing

Two plants, two hyperscalers, and numbers nobody quite agrees on

Neither plant exists in a vacuum, and neither is a mystery about who it's for, even where the public record stops short of a signed confirmation. Foundry Ridge has been understood since the gas-plant status update in this blog's Oracle/Point Beach post last week as a plant built for We Energies' Project Lighthouse customer, the Oracle/Vantage Data Centers/OpenAI campus in Port Washington — what that post flagged three weeks ago as a filing still working through Wisconsin's process is now an approved, if conditional, project. Red Oak Ridge's customer took longer to surface: a Racine County Eye report from August, since unconfirmed by any Invenergy or We Energies statement I could find, says Microsoft has already signed up to buy power from the plant for its Mount Pleasant campus, the former Foxconn site. We Energies, for its part, has pending applications to buy both plants outright from Invenergy once they're built — a combined purchase reported between $2.2 and $2.3 billion, with Red Oak Ridge's piece alone put at $1.7 billion in one account and $1.77 billion in another. None of those discrepancies change the shape of the deal. They're a reminder that even a project this large doesn't come with one clean, agreed-upon number until the underlying contracts are public.

We Energies hasn't gotten approval to actually buy either plant yet. That's a separate docket, still pending, from the certificate Invenergy just won to build them. Under Wisconsin's merchant-generation rules, the commission reviews the developer's right to build and the utility's right to buy as two different questions, decided at two different times — a structure PSC commissioners themselves said limits how much oversight either review can really apply.

The one real win buried in the same system

Here's where the story stops being only bad news. Back on April 24th, the same commission ruled on a separate but related fight: how much of the cost of generation built specifically for data centers gets passed on to everyone else. We Energies had proposed letting data centers cover 75% of the cost of new, dedicated power plants, with the remaining 25% folded into the rates every other customer pays. The commission said no. It now requires large customers, lowering the qualifying threshold from 500 megawatts to 100, to cover 100% of the cost of generation built for them, under mandatory 10-to-15-year agreements, with financial guarantees required from any developer rated below A-.

A significant and consequential tariff docket unlike anything the commission has seen before.Summer Strand, PSC of Wisconsin chair, on the April data-center tariff order

That's a real structural protection, not a press-release promise, and it's the same kind of mechanism this blog has tracked in Michigan's DTE/Google contract and Virginia's Dominion GS-5 rate class: make the customer causing the cost carry the cost, by rule, before the plant gets built rather than after a rate case fights over who pays. Wisconsin ratepayers outside the two data centers in question are, on paper, protected from footing this particular bill.

On paper is the operative phrase. In June, two months after that order, We Energies asked the commission to loosen the credit-guarantee rule the same tariff depends on, telling regulators that the hyperscaler behind one of these deals carries a BBB credit rating, a notch below the A- threshold the rule assumes a large-load customer will clear. A rule built to make sure a well-capitalized customer, not Wisconsin ratepayers, is on the hook if a deal falls apart is only as good as the credit standard behind it, and the utility that has to enforce that standard against its own multi-billion-dollar customer is the same one asking to soften it four months in.

A contract that's already out of date

There's a second gap worth more attention than it's gotten. In May, the commission voted to strip a geographic restriction out of We Energies' large-load rules, one that had required any dedicated generation serving a big customer to sit within eastern Wisconsin or Michigan's Upper Peninsula. Two months later, in July, We Energies signed a contract with Microsoft for its Mount Pleasant load that still contains that same restriction, word for word, according to Wisconsin public broadcasting's reporting on the deal. We Energies says it intends to follow the commission's order rather than its own contract's language, and that it's working with regulators to resolve the mismatch. Maybe that's a clean fix. But a signed commercial contract that already conflicts with the regulatory order meant to govern it is exactly the kind of fact GridPermit's own diligence framework treats as unresolved rather than settled — a document that exists is not the same thing as a document that's internally consistent with the rules it operates under, and the gap between the two is where a deal that looks finished from a press release turns out not to be.

Back in Kenosha County, Hannah Schlick told the commission the developer was preying on a rural community for profit. In Paris, Kaley Zalubowski said she worries what the plant's emissions could mean for her son, who has asthma. Those aren't abstractions weighed against a capacity number on a spreadsheet; they're the actual terms residents are being asked to accept, in exchange for a plant whose own developer, Invenergy's Daniel Birmingham, says will "help stabilize costs and meet electricity needs during periods of peak demand." Both things can be true. A grid under real strain from data-center growth does, in fact, need more dispatchable generation somewhere. That doesn't make the specific tradeoff easier for the people living 650 yards from where it gets built.

I don't think Wisconsin's regulators got this one simply wrong. Strand's own framing, that the gaps here are a legislative problem and not just a commission problem, is the more honest read: state law lets a merchant developer skip the "is this actually needed" test a utility-built plant would face, and lets the DNR's air permit decision functionally override local opposition once it's granted. The commission applied the law it has, not the law critics wish it had. What's genuinely new and worth crediting is the April tariff order sitting underneath all of this, the rule that stops Wisconsin households from quietly absorbing part of the bill for someone else's data center. Whether that rule actually holds, against a credit standard already under pressure to loosen and a signed contract that's already out of step with the order governing it, is the real test still ahead. The gas plants are approved. Whether the protection built around them survives contact with the companies it's supposed to bind is not decided yet.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report