November 18, 2026 · Brendan Hogan, Founder, GridPermit

PJM Just Told FERC How It Will Stop the Next 3,800-Megawatt Grid Drop. Who Pays For the Upgrades Behind It Is Still Somebody Else's Call.

PJM met a federal deadline on data-center grid rules November 16th, with a real fix for the reliability risk. Four states' ratepayer advocates say the cost question is still unanswered.

On June 18th, the Federal Energy Regulatory Commission did something it doesn't do lightly: it opened a formal show-cause proceeding against PJM Interconnection, the grid operator responsible for keeping the lights on for roughly 65 million people across 13 states and Washington, D.C. A show-cause order isn't a request for comment. It's FERC telling a regulated entity that its existing rules look unlawful on their face, and giving it a deadline to prove otherwise or fix them. FERC's order, docketed EL26-67, found that PJM's tariff for connecting large loads like data centers appeared "unjust and unreasonable," partly because the rules gave PJM no way to require that a data center's own grid upgrades get paid for by the data center, rather than quietly spread across every other customer on the system. PJM's transmission owners got one extension, to November 16th. After that, the clock ran out.

PJM made the deadline. On November 16th, it and its transmission owners filed two things with FERC, and the gap between them is the real story.

The reliability half: an actual fix for an actual failure

The first filing answers a question this blog raised a month ago. On July 22nd, a single transmission line tripped in Dominion Energy's Northern Virginia territory, and in the next 91 seconds roughly 3,800 megawatts of data center load -- the largest load swing PJM has ever recorded -- switched itself over to backup generators almost all at once. NERC responded with a final, binding reliability standard on October 15th, but PJM had already told FERC it planned to file its own interim version first. It did: new "large computational load" ride-through rules covering any site of 50 megawatts or more at 100 kilovolts or above, requiring those sites to stay connected through a normal voltage or frequency disturbance instead of treating it as a cue to unplug. Crucially, the rules aren't limited to the next data center built. They reach the ones already running, with PJM saying it will work out a transition plan directly with existing operators rather than grandfathering them out entirely. FERC is asked to rule by January 15th, 2027.

That is a real fix, aimed at a real, measured, worsening problem, arrived at through the process FERC's order was designed to force: a federal regulator set a hard deadline, and the grid operator answered it with an enforceable rule rather than a voluntary pledge. It's the kind of outcome this blog doesn't get to report on often.

The cost half: visibility, not an answer

The second filing is where PJM's own language gives away the limits of what it just did. The filing would require PJM to show states exactly how much of a data center's transmission-upgrade cost is being charged against the broader system, rather than burying it in a regional cost pool nobody outside the filing can trace. States could then use their authority over retail rates to decide whether to bill that cost directly to the large load responsible for it. That's a meaningful change from today, where a state regulator often can't even see the number clearly enough to have the argument. But PJM was explicit, in its own filing, that it "does not control how those costs are allocated" once they're visible -- that decision is left to each transmission owner's own tariff, filed separately, utility by utility, under a companion proceeding. Visibility is not the same thing as an answer.

Ratepayer advocates in Delaware, Illinois, Maryland, and Ohio said as much within days of the filing, arguing to FERC that the framework still doesn't require data centers to cover the full cost of the network upgrades their own load triggers -- only that someone, eventually, gets to see the bill before deciding who pays it. That's consistent with the fight the Maryland Office of People's Counsel has been having with PJM all year, in a separate proceeding, over roughly $5.1 billion in Northern Virginia-driven transmission costs it argues should fall more heavily on the zone that caused them. FERC has already rejected Maryland's ask once. Nothing in November 16th's filing settles that argument; it just moves it from "we can't see the number" to "we can see it, and we're still fighting about who pays it."

The smaller fight that actually matters here

There's a quieter argument running underneath both filings that I think is more consequential than either one on its own. Neil Osnato, founder of the consultancy Persistence Analytics Group, has written that PJM is in the process of separating "connected" from "firm" -- that having a signed interconnection agreement has, until now, functioned as an unofficial guarantee of reliable service, even though nothing in that agreement actually proves the load behind it is real, final, or ready. His own framing of it: don't grant firm-service economics against an unverified capacity or load claim. PJM's independent market monitor, Joseph Bowring, has pushed the same point from the other direction, arguing that a large load's claims about its own size and timeline need ongoing validation, not a one-time entry in a registry. PJM says it has already tightened its vetting; Bowring's office disputes that it's enough, and the two sides have been filing past each other on it for most of this year.

I think that's the part worth sitting with longer than the headline numbers. Every large-load tariff this blog has covered -- Michigan's, Oregon's, Texas's, Florida's -- eventually comes down to the same question: is this commitment something a utility, a county, or a regulator can actually hold someone to, or is it a number on a form nobody has checked? PJM spent five months answering FERC's deadline with a real fix for a grid that had already proven it could fail, and a genuine step toward making the cost of the next upgrade visible. What it didn't do is answer who pays when that number comes due. Four state ratepayer offices just told FERC, in writing, that the gap is the whole argument.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report