November 13, 2026 · Brendan Hogan, Founder, GridPermit

Duke Energy's First Florida Data Center Tariff Hinged on the Word 'Firm.' Regulators Rejected It, 5-0.

Florida's new law makes data centers cover their own power costs. Duke Energy's first attempt to comply defined 'large load' more narrowly than the statute does, and the PSC voted 5-0 to send it back.

On November 3rd, Florida's Public Service Commission voted 5-0 to reject the first tariff any utility in the state had filed under a four-month-old law written to keep data center costs off ordinary customers' bills. Duke Energy Florida wrote that tariff. The fight over it came down, in the end, to one word: "firm."

A law built around one number

SB 484, signed by Governor Ron DeSantis in May and in effect since July 1st, was Florida's answer to a question other states were already fighting over: when a data center shows up asking for tens or hundreds of megawatts, who pays to build the power plants, substations, and transmission lines that serve it? The law's answer is that a "large-load customer," defined as anyone with an anticipated monthly peak of 50 megawatts or more at a single location, measured as the highest average load over any 15-minute interval, has to cover its own full cost of service. Residential customers and small businesses aren't supposed to subsidize the buildout. Duke Energy Florida's large-load tariff, filed in Docket No. 20260064-EI, was the first attempt by any utility in the state to turn that sentence into an actual rate schedule.

SB 484 didn't appear out of nowhere. Florida lawmakers wrote it, Chapter 2026-65, Laws of Florida, after a year of warnings from consumer advocates that the same fight already playing out in Virginia, Georgia, and Ohio, utilities asking regulators to let data center buildout costs flow into everyone's bill, was about to land in Florida too, as hyperscale projects kept announcing themselves up and down the state. Governor DeSantis signed the bill on May 7th, and it took effect July 1st, giving every investor-owned utility in the state a brand-new statutory line to write its next large-load tariff around. Duke went first.

The problem, according to the Office of Public Counsel and a grassroots group called Florida Rising, was in how Duke translated the statute. SB 484 measures the threshold by what a customer's load actually does: its anticipated monthly peak, however that power is contracted. Duke's tariff applied the 50 MW threshold only to customers who formally request firm, guaranteed, uninterruptible service. A data center that instead took power on a non-firm or curtailable basis, while still drawing something close to continuous load month after month, would never trigger the tariff at all, even at 200 megawatts. That's not a hypothetical edge case. It's the exact kind of load the law was written to catch, routed around the definition meant to catch it.

Who said so, and who Duke tried to remove from the case

Florida's statutory ratepayer advocate, the Office of Public Counsel, led by Walt Trierweiler, argued the petition didn't comply with SB 484 as written. Florida Rising, a Tampa-based organizing group with no obvious financial stake in the outcome, intervened alongside them, represented by Earthjustice attorney Bradley Marshall. Duke's lawyers moved to have Florida Rising removed from the case entirely, arguing the group had only limited connections to Duke's own customers. The commission let Florida Rising stay. At the August 25th-26th evidentiary hearing, Marshall put the stakes plainly: if the data center investment now flooding Florida ever slowed or stalled, "the general body of customers will be left holding the bag."

Commission staff reviewed the record for two months and recommended, on October 22nd, that the full commission deny Duke's tariff as filed, with leave to refile. The commissioners followed that recommendation on November 3rd. Five votes, zero dissents. Not a split decision anyone could spin as a close call either utility or customer could claim.

Two ways to read the same rejection

Duke's own read of the loss was measured. Spokesperson Ana Gibbs said the company "appreciates the Florida Public Service Commission's careful review" and remains focused on supporting growth while protecting costs for customers, language that treats this as a drafting correction rather than a defeat. Duke now has to submit a new large-load rate schedule, this time with evidence that qualifying customers actually bear their own cost of service, before any data center in its territory gets billed under a rate the PSC has actually blessed.

Advocates read the same outcome differently. Food & Water Watch's Florida director, Brooke Ward, framed the rejection as proof the new law is doing exactly the job legislators built it for: blocking a utility from shifting data center costs onto families and small businesses, on the first real attempt to test whether it would. Both readings can be true at once. Duke will very likely get a compliant tariff approved eventually; Florida has every incentive to keep the hyperscale investment coming, and SB 484 was written to make that investment possible, not to block it. But "eventually" is doing real work in that sentence, and every other Florida utility serving large-load customers right now, FPL and TECO included, was watching Duke go first specifically so it wouldn't have to find this gap in its own filing the hard way.

It's also worth saying plainly that Duke isn't a small player improvising under a new rule it never saw coming. The company has its own multi-billion-dollar Florida capital plan built in part around serving exactly this kind of growth, and it had a full year between the bill's signing and its own filing to get the definitions right. A tariff that quietly narrows a 50-megawatt statutory threshold down to customers who check a specific contractual box isn't the kind of mistake that survives a careful legal read before filing, which is presumably why the Office of Public Counsel and Florida Rising caught it almost immediately and why PSC staff agreed with them two months before the commission ever voted.

What this means if you're sizing a Florida site today

This is precisely the kind of gap GridPermit's own diligence process is built to catch before it becomes a surprise three years into a power contract: not whether a utility has a large-load tariff on file, but whether the tariff's own definitions actually match the statute that's supposed to govern it. A large-load tariff is a risk allocation before it's a price, and a developer modeling costs off Duke's rejected filing right now would be modeling off terms the PSC has explicitly said don't comply with Florida law. The same scrutiny is showing up everywhere states are writing their own version of this fight; Virginia's SCC spent a full rate case forcing Dominion to rework who actually pays for new transmission capacity, and Florida just spent four months, a failed motion to dismiss, and a two-day hearing finding out that writing the rule and writing a tariff that actually follows it are two different jobs.

The real headline out of Tallahassee isn't that Duke lost. It's that there is currently no large-load tariff on the books anywhere in Florida that has survived contact with the law it's supposed to implement. Whatever Duke files next, and how closely its definitions finally track the statute's own language, will tell every other Florida utility, and every other state about to write its own version of SB 484, whether Duke's first attempt was an honest drafting mistake or a starting position it expected regulators to talk it down from.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report