November 3, 2026 · Brendan Hogan, Founder, GridPermit

Amazon's Louisiana Data Centers Just Grew to $18 Billion. A Job Fair on November 17th Is the First Real Test of the Promise.

Amazon's Shreveport-area data centers grew from $12 billion to $18 billion in nine months. Nobody's published yet how many of the promised 750 jobs will go to someone who already lives in Caddo or Bossier Parish.

On the morning of November 17th, Amazon is holding a job fair inside a public school. The Bossier Parish Schools Center for Technology and Innovative Learning will host career presentations for a company that, as of nine months ago, had never built anything in Louisiana. Two more sessions follow on the 18th and 19th at North Louisiana Technical Community College. The pitch is straightforward: paid apprenticeships, a path into data center operations, and a shot at one of roughly 750 permanent jobs Amazon now says its data center buildout across Caddo and Bossier parishes will eventually support.

That number is bigger than it used to be, and so is the project behind it. When Governor Jeff Landry stood in Shreveport last February and announced Amazon's first-ever Louisiana data center campuses, the figure was $12 billion, spread across what the state described as two sites. STACK Infrastructure, the developer building for Amazon, projected up to 1,500 construction jobs and roughly 540 permanent ones, with the state's economic development office adding another 1,700 indirect jobs on top. Nine months later, the investment is up to $18 billion, the site count is three, and the permanent-jobs estimate has grown to about 750 — real growth, not a rounding error, in one of the poorer corners of the state.

Real growth isn't the same thing as a finished promise. A Red River Dispatch investigation published October 18th asked the question nobody at the press conference had to answer: of those 750 jobs, how many actually go to someone who already lives in Caddo, Bossier, or De Soto parish? The region has real strength in the trades a data center needs — electricians, HVAC technicians, security — but a thin existing technology workforce, and the regional labor numbers Amazon and the state point to describe every employer in the area, not the specific pool Amazon will actually hire from. The reporting's real contribution wasn't skepticism for its own sake. It was a short list of numbers nobody has published yet: completion rates out of the training pipeline, placement rates into real jobs, and the share of hires who had a local address before the apprenticeship started.

What the power company is actually promising

The clearest, most testable commitment so far isn't about jobs. It's about who pays for the power. Southwestern Electric Power Company, the AEP subsidiary serving northwest Louisiana, says Amazon is covering the full cost of the new substations, transmission lines, and specialized equipment the campuses need, not existing residential and business customers. That's the same basic structure Georgia's electric co-ops, Ohio's AEP tariff, and a half-dozen other utilities have adopted for data center load this year, for a simple reason: it's the only version of this deal that doesn't eventually land on a residential bill.

Louisiana Public Service Commissioner Foster Campbell, whose district covers the project, has put himself on the record backing the arrangement.

I've been assured by SWEPCO and Amazon that electric bills will not go up because of this data center, and I intend to hold them to that. People's bills are already high enough without piling a new data center on top of them.Foster Campbell, Louisiana Public Service Commissioner

Campbell has called the project a good way for one of the largest companies in the world to start investing in a poor region, and he isn't hedging that judgment. But the promise he's vouching for is still a commercial arrangement backed by his own public confidence, not a line-item tariff the full Commission has reviewed and approved the way it has for SWEPCO's broader system-improvement plan. On GridPermit's evidence ladder, a commissioner's assurance is real information. It isn't the same rung as an approved rate schedule, and the ratepayer with no vote on either one is the one who'd actually feel the difference.

The fight over water Amazon mostly won't drink

Amazon's water pitch follows the same shape as its power pitch: pay for the upgrades, promise restraint, and point to a reassuring number. The company says its Louisiana campuses will rely on air cooling more than 87% of the year, pulling water only during the hottest summer stretches and only water that is "verified surplus" beyond what the community needs. It has also pledged up to $400 million toward public water and sewer infrastructure in the Caddo-Bossier area and says it's working toward being "water positive" there by 2030.

The numbers on the ground are less tidy than the pledge. The town of Blanchard, which draws its own water from Caddo Lake under a 99-year contract with neighboring Mooringsport, approved a deal last December letting the Amazon-linked State Line campus pull up to 5 million gallons a day, starting around 1.3 to 1.4 million gallons and growing toward 3 to 4 million as the site builds out. Blanchard's own peak daily use today is about 3.5 million gallons. Amazon is paying for the new infrastructure, so the mayor says residents won't see a rate increase — the same assurance SWEPCO is making about electricity, hitting the same limit: a mayor's word isn't a rate case any more than a commissioner's is.

Not everyone on the Caddo Parish Commission is willing to take that on faith. Commissioner Chris Kracman pushed a resolution in January asking the state and the Red River Compact Commission to pause large new withdrawals from Caddo Lake for a year, or until someone actually studied what the lake could sustain. It died in a work session without a single commissioner seconding it. A broader, parish-wide push to have the Planning and Zoning Commission study a data center moratorium failed 6-4 a few months later. Kracman hasn't let it go — "I don't think it's over," he told a local reporter — and he's now pursuing a water study instead of a moratorium: a narrower ask, but one aimed at an actual number instead of competing assurances.

A separate, Sierra Club-backed lawsuit over the Shreveport-area project's permitting process lost at the trial court level in April. The plaintiffs appealed in July, and the Second Circuit Court of Appeals still hadn't scheduled a hearing as of this fall. Nobody seriously following the case expects it to stop the buildout. What it has done is add nine months, and counting, of legal uncertainty to a project the state keeps describing as a sure thing.

I think the honest way to read this story is that Amazon has done the easy part of the deal well: write the check, fund the substation, cap the first phase of water use. The hard part is still unverified. Whether the apprenticeship slots turn into real careers for people who already live in Caddo and Bossier parishes, and whether "verified surplus" water holds up the first time Shreveport has a dry summer, are both questions nobody can answer yet. November 17th is a job fair, not a jobs report. The number worth watching over the next year isn't $18 billion. It's how many of the people walking out of that school in Bossier Parish are still on Amazon's payroll twelve months from now, and how many of them had a Caddo or Bossier Parish address before they ever walked in.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report