October 24, 2026 · Brendan Hogan, Founder, GridPermit

Memphis Banned a State Lawmaker From City Hall Over a Data Center Vote. A Federal Judge Said That Part Wasn't Legal.

A council meeting on Elon Musk's data centers got so heated that Memphis banned a sitting state representative from City Hall. A judge reversed that in days. The yearlong moratorium it was fighting over still failed on a 6-6 tie.

On October 8th, Memphis City Council Chairwoman Jana Swearengen-Washington sent a letter barring four people from the council's next two scheduled meetings: state Rep. Justin Pearson, and organizers Amber Sherman, LaJuana Abraham, and Jasmine Bernard. Local reports put the broader number of people removed from the chamber that day at six. Their offense, as the council saw it, was being in the room on October 6th when a vote on a proposed yearlong data center moratorium turned into a shouting match loud enough that police cleared the chamber. A federal judge took about a week to tell the council it couldn't do that, not without rules nobody had actually written down. The moratorium itself fared almost as badly. Two weeks after the ban, the council let the yearlong pause die on a 6-6 tie and settled for something much narrower instead.

The meeting that got people banned was supposed to answer a straightforward question: should Memphis stop approving new data centers for a year while the city figures out what it's gotten itself into. This blog covered the lead-up to that vote on October 4th, when the ordinance looked headed for majority support on its third reading. Two days later, it didn't even get called. More than 100 members of the public packed the chamber that day, by local reporting, most of them opposed to the data center boom reshaping their city, and most of them there because of one company. xAI, Elon Musk's AI venture, has built two giant computing campuses in the Memphis area over the past two years, Colossus in South Memphis and a second site, Colossus 2, just across the state line in Southaven, Mississippi. The meeting never reached a vote. Seven council members voted to postpone it, five wanted a decision right then, and in the meantime protesters chanted, a shoving match broke out in the City Hall lobby, and officers cleared the room. The council didn't finish its business that day. It banned several of the people who'd shown up to make their case.

Pearson is a familiar name in Tennessee politics, a Memphis-area state representative who's been at the center of fights with state and local power before. His lawsuit against the council argues the ban violated his First Amendment right to attend and speak at public meetings, and separately alleges his home address was exposed online, which he attributes to state Sen. Brent Taylor. The council's own decorum rules allow removing someone from the meeting where they caused a disruption. They say nothing about barring someone from meetings that haven't happened yet, which is exactly what the October 8th letter did, covering both the October 10th and November 10th sessions.

U.S. District Judge Thomas L. Parker didn't let that stand. He granted Pearson and the three organizers a temporary restraining order, writing that while the council has a real interest in keeping its meetings orderly, the public interest favors open debate, especially over unpopular ideas. Reports differ on exactly how far his order reached, but the practical result was clear: a ban imposed without any written standard for who gets barred, or for how long, didn't survive its first test in federal court.

Two weeks later, on October 20th, the underlying fight came back to the council floor, and it went about as well for moratorium supporters as the process that got there. With council member Yolanda Cooper-Sutton absent for a family emergency, Ordinance 19, the measure that would have paused new data center approvals for a full year, died on a 6-6 tie. Councilman J.B. Smiley Jr., the ordinance's sponsor, had pushed for a final vote rather than another delay, pointing to what he called a lack of transparency and community engagement in how the city's data center boom had unfolded in the first place.

In the moratorium's place, the council passed Ordinance 18: a 135-day pause on new data center permits and applications, timed to run alongside a 90-day study of large-load development that Memphis Mayor Paul Young had already ordered at the start of October. The shorter measure is explicit about what it doesn't do. It doesn't touch anything already built or permitted. xAI's existing Memphis facilities keep running exactly as they have, and the pause only reaches whatever comes next.

Amber Sherman, Tennessee lead organizer for Black Voters Matter and one of the four named in the since-lifted ban, didn't pretend the outcome surprised her. "I'm very disappointed, very disheartened," she said after the vote. "Definitely not surprised, though. I think that this council has shown a history of not siding with people unless immense pressure is applied." It's a fair description of the sequence that just played out: a year's worth of organizing produced a tied vote and a pause measured in months, not the pause activists had been asking for.

The permit question the vote never touched

The anger in that chamber didn't start with an abstract worry about data centers in general. It started with a specific, checkable claim about one company's equipment. Shelby County's health department approved an air permit in 2025 covering 15 gas turbines at the Colossus site, rated at roughly 247 megawatts combined, running through January 1, 2027. Lawyers for the Southern Environmental Law Center, representing the NAACP, say aerial imagery showed as many as 35 turbines operating on site at times, more than double what the permit allows, in a part of South Memphis that already carries a heavier industrial pollution burden than most of the city. Violations of that kind can carry fines of up to $10,000 per turbine, per day. xAI has said it began removing turbines and would rely on gas generation only as backup once a second substation came online. I didn't find anything published in 2026 confirming whether that actually happened, or where the compliance dispute stands today. The NAACP and its Mississippi State Conference filed a separate lawsuit in April over similar unpermitted turbines at the Southaven site, which that complaint describes as a power plant built without the permits or public notice a facility that size would ordinarily require.

The mayor's office has its own numbers, and they're real ones. xAI paid roughly $25 million in property taxes in its first year in Memphis, Young's office says, making it one of Shelby County's largest taxpayers. The company also funded an $80 million water treatment facility, built specifically to reduce the operation's draw on the Memphis Sand Aquifer, the same source much of the region depends on for drinking water. Both of those facts can be true at the same time as the turbine dispute. A company can be a major, legitimate local taxpayer funding real infrastructure and still be the subject of a live, unresolved question about whether it's running twice the pollution-generating equipment its own permit allows. The council's vote didn't adjudicate that question either way. It wasn't built to.

What 135 days actually buys

What the pause buys Memphis is time to write rules for the next data center, not an answer about the one already running. That's a genuinely different fight from the one playing out across the state in Nashville, where a federal judge dismissed a zoning-and-eminent-domain lawsuit over a different company's data center near the city zoo, on the theory that the project's permits were already vested under the city's own rules. Nashville's fight was about whether a project followed the zoning process correctly. Memphis's fight is about whether a company is complying with an environmental permit it already has, which is a question local rezoning authority can't touch and a 135-day building pause doesn't answer either.

I think the moratorium vote is the least important thing that happened in Memphis this month, even though it's the part that made national news. A 135-day pause on new permits does nothing to resolve whether the turbines already running at Colossus ever matched the permit the city granted, and that question has a real, dated deadline attached to it that no council vote changes: the existing permit itself expires January 1, 2027. Whatever the mayor's 90-day study recommends, and whatever the council does with it, that date is the one actually worth watching. A city can ban a lawmaker from its own meetings for a week and get overturned by a judge just as fast. Getting an honest count of how many turbines are actually running behind a fence line takes longer than that, and matters more.

← Back to the blog

Evaluating a specific parcel for a 50–300 MW load? GridPermit's Preliminary Site Kill Test grades the power, zoning, water, and commercial-readiness evidence before you buy the land.

Start a Qualification Review

See state-by-state coverage · Read the methodology · See a sample report